Main features of Cummins PT pump fuel system

Main features of Cummins PT pump fuel system:

In the PT pump fuel system, the fuel generates high pressure, and the timing distribution and fuel volume adjustment are in the fuel pump. In the fuel pump and fuel injector fuel system, the fuel generates high pressure, and the timing distribution and fuel volume adjustment are in the fuel pump and the injector, only about 20% of the fuel entering the injector is injected into the combustion chamber from the fuel injector, the remaining fuel cools and lubricates the injector and returns to the fuel tank.

Because the fuel pump in the PT fuel pump system only outputs low oil pressure without high-pressure fuel pipes, there is no problem of pressure waves at high speed, and the driving speed under the injector plunger is fast, the size of the injection hole is small, so the injection pressure can reach 100MPa, which is beneficial to combustion atomization, full combustion, and good economy. It can be seen that Cummins PT fuel system plays a vital role in the operation of Cummins diesel generator.


Cummins diesel generator

The test bench debugging method of Cummins PT fuel pump is as follows:

 Install the fuel pump on the test bench. After the fuel pump is connected to the drive plate, fill the pump housing and the oil inlet hole of the gear pump with clean test oil from the plug hole at the top of the fuel pump. Connect the oil inlet rubber hose and the cooling oil drain valve hose; check whether the voltage stabilizer is stable to ensure that the gear pump works stably; adjust the pointer of each measuring instrument to zero position.


 Trial run. Close the idle small orifice valve, throttle valve and leakage valve on the test bench, and fully open the vacuum adjustment valve, oil cut off valve and flow adjustment valve. The throttle valve of the fuel pump is in the fully open position, and the double arm lever of the MVS governor is in contact with the high speed limit screw. Start the motor to make the fuel pump run at 500r / min. If the fuel pump does not suck oil, check whether the valve in the oil inlet line is open, whether there is air leakage, or the rotation direction of the fuel pump is reversed; test run for more than 5 minutes to allow air to be discharged from the oil and the oil temperature rises to 32~38.


 Check the tightness of the fuel pump. At a speed of 500r / min, close the vacuum adjustment valve while opening the flow adjustment valve, the vacuum meter reading should be 40kPa; apply a small amount of light grease to the vent hole at the main shaft sealing device of the front cove of the fuel pump, no inhalation means good  seal; Check the tightness of the O seal ring of the throttle valve, the seal ring hole of the chronograph, the double arm lever shaft of the MVS governor and the adjusting screw, the gasket between the gear pump and the housing. If there are air bubbles in the fuel of the flowmeter, it means that air has entered the fuel pump in the above part.


 Adjust the vacuum. Fully open the flow adjustment valve on the test bench, the fuel pump runs at the rated speed of the diesel engine, and adjust the vacuum adjustment valve to make the vacuum meter reading 27kPa.


 Adjust the flow meter. The fuel pump runs at the nominal speed of the diesel engine, and the flow adjustment valve is used to adjust the float of the flow meter to the specified value.


 Adjust the speed of the disconnection point of the governor. The throttle valve is fully open, increase the speed of the fuel pump until the fuel pressure begins to drop, and check whether the speed of the fuel pump's disconnection point is within the specified value. If it is lower than the specified value, a gasket can be added between the adjusting spring and the snap ring; otherwise, the gasket should be removed. When the MVS governor is installed, it is adjusted with a high speed limiting screw.


 Check the fuel pressure point. Increase the fuel pump speed. When the fuel pressure drops to 276kPa, check whether the fuel pump speed is within the specified value range. Make the fuel pump continues to increase the speed, the fuel pressure should be able to reduce to zero, otherwise the fuel in the fuel pump is short-circuited.


 Commissioning of fuel outlet pressure at nominal speed and maximum torque point speed. Starting from zero fuel pressure, reduce the speed of the fuel pump to the calibrated speed and check whether the fuel outlet pressure meets the specified value. When the MVS speed governor is not installed, use the increase or decrease gasket to adjust. When the MVS governor is installed, use the throttle adjustment screw to adjust; when the fuel pump speed drops to the maximum torque point speed, check whether the fuel outlet pressure meets the specified value.


 Adjustment of idle speed and fuel outlet pressure. Close the throttle valve, leakage valve and flow adjustment valve on the PT pump test bench, open the idle orifice valve, make the throttle valve shaft of the fuel pump in the idle position, make the fuel pump run at idle speed, and check whether the fuel outlet pressure meets the specified value. Adjustable with idle speed adjustment screw.


Hope the above methods help you debug the PT pump of Cummins diesel generator well.


Starlight Power specializes in manufacturing diesel generator set more than 40 years. As Cummins diesel generator OEM manufacturer, Starlight can provide 20kw to 2500kw high quality open / silent diesel generator powered by Cummins engine. If you are interested, please contact us for the latest quotation.

Comments

Popular posts from this blog

Yuchai Is Super Confident in Its Innovation

Founded in 1951, with 30 wholly-owned, holding and joint-stock subsidiaries, Guangxi Yuchai Machinery Group Co., Ltd. (hereinafter referred to as the Yuchai Group) is an internal combustion engine manufacturing base with the most complete spectrum of products in the country. In recent years, machinery manufacturing industry has been dropped off influenced by domestic and foreign economic situations, especially domestic overcapacity and unreasonable product structure. Reversely, Yuchai has sold over 3 million engines with the annualized revenues amount to RMB 40 billion. Over the years, as China ’ s largest engine R&D manufacturing base, Yuchai adjusts and optimizes its industrial structure and constantly strengthens its capacity for independent innovation. Therefore, the key technology continues to be the top in the sector for further keeping its own top leader in the industry. Innovation-Driven In 2013, seven world-class diesel-engine products for high-s...

How to Read Alarm Codes From SmartGen Genset Controller

Auto Module Control Panel is the configuration for nobody on duty controlling generators. This kind of panel adopts auto module control system, with large LCD display to show the menu, such as SmartGen controller. Features:   1. SmartGen 6110 can receive remote output signal from ATS and realize auto start and stop of generators. 2. SmartGen 6310 can realize all functions of 6110, add RS232 interface which can communicate with PC to realize remote operation.  3. SmartGen 6410 Auto Mains Failure controller, can realize all functions of 6310, furthermore can detect  ATS and control directly. The alarm of diesel generator controller is not the amount of stop alarm, which does not affect the normal operation of diesel generator. When the alarm occurs, the unit will not stop, and when the alarm conditions do not exist, the amount of warning will automatically disappear.  Today Starlight manufacturer mainly shares alarm codes for diesel generato...

How to know and solve faults of genset voltage transformer

 Today Starlight Power shares the common faults for voltage transformer of diesel generator set. Hope it is helpful to you. 1) The insulation between iron chips is damaged. Fault phenomenon: temperature rises during operation. The possible causes of the failure are: poor insulation between iron chips, bad use of environmental conditions or long-term operation under high temperature, which promote the insulation aging between iron chips. (2) Poor contact between grounding plate and iron core. Fault phenomenon: there is discharge sound between iron core and oil tank during operation. Cause of failure: the grounding plate is not inserted tightly, and the mounting screw is not tightened. (3) The iron core is loose. Fault phenomenon: abnormal vibration or noise during operation. The cause of failure: the iron core clamp is not clamped, and the iron chip is loose. (4) Turn to turn short circuit of winding. Fault phenomenon: during operation, the temperature rises, there is ...