The diesel generator and voltage regulator have been had matching test at the factory. Therefore, when loading and using, the 200kw Cummins genset and voltage regulator shall be installed and used together with the same number and the same ex factory date. Only acceptance test shall be carried out by the user. If the generator and voltage regulator are overhauled, the components affecting the electromagnetic performance have changed, or the number of the generator and voltage regulator are different, the matching test must be carried out. The test steps are as follows: 1.Appearance inspection: the generator and voltage regulator shall be intact, all screws shall be free of looseness, and the rotor shall rotate flexibly without friction, otherwise, they shall be disassembled for inspection. 2.Connect the steam pipe, connect the high-pressure steam, no-load for several minutes, and measure the speed within the rated range. Measure the voltage between the tw...