Main installing requirements of Diesel engine

1. Installation of the crankshaft
During crankshaft installation, the main bearing bolts should be tightened from thrust gear(the third gear) to both ends in order, and in three steps:
① tighten to 60-80 N.m
② tighten to 160-180 N.m
③ tighten to 220-260 N.m
During every time, the crankshaft should be rotated to check the mobility. It should be able to rotate freely after the final tightening.The axial clearance should be between 0.1 and 0.27 mm.

2. Installations of the piston and the connecting rod
When installing the piston rings, put the surfaces marked upward( the second positive twist ring inner fillet upward). During positioning the piston-connecting rod assembly into the cylinder bore, stagger the joints in turn. And put the arrow marked on the top surface of piston towards the front end of the engine. Remember spreading some clean oil before tightening connecting-rod bolts. The tightening torque should be between 160-200N.m, and completed in three steps:
① tighten to 50-70 N.m
② tighten to 100-120 N.m
③ tighten to 160-200 N.m

3. Installation of the camshaft
Position the camshaft into the cylinder body with caution to make sure not scratch the surfaces of the journals, cams, and liners. And then install the cir clip, cam thrust plate, cam gear, and cam retainer, Finally,tighten fastening bolt with more than 300N.m tightening torque. The camshaft should be able to rotate freely, and its axial clearance is between 0.1-0.2mm.

4. Installation of the valves and valve guides
The valve guides should be pressed in at normal state with 20±0.3mm distances between their top surfaces and the surfaces of the cylinder head spring seats. Both the valve face angles of intake and exhaust valves are 45º. the valves and valve seat inserts should be grind in pair, and checked through kerosene. It must be guaranteed that kerosene do not leak within three minutes. The valve recession heights of the valves should be between 1±0.2mm.

5. Installation of the injectors
Before mounting the cylinder head, the injectors should be installed in the cylinder head first. The nozzles should protrude 3.4±0.1mm from the bottom surface of the cylinder head, which can be ensured by adjusting the width of the injector washer. And then remove the injectors to prepare for following installation. As long as adjusted, the injectors and washers can not be exchanged during installation.

6. Installation of the cylinder head
During cylinder head installation, the cylinder head bolts should be tightened to a tightening torque of between 210-250 N.m, do not finish that in once time and following the sequence shown in the following figure by three steps:
① tighten to 60-80 N.m
② tighten to 120-140 N.m
③ tighten to 210-250 N.m


7. Installation of the gear train
The crankshaft timing gear, injection pump gear, and camshaft gear should all be accordance with the timing requirement, so there are timing marks, which should be aligned during installing the gears, on them and timing idle gear. Oil the tooth surface after installing. The range of the gear meshing clearance is between 0.07-0.25mm.

Caution
1. every component should be cleaned before being installed, especially the oil passages, no dirt is permitted in them.
2. No corrosion, burr, or scratch is permitted on the fit surfaces of every component.
3. Friction surfaces and important fit surfaces should be oiled before installing.
4. Fit clearance( or interference) should be accordance with the requirement offered in the main fit clearance(or interference).

Comments

Popular posts from this blog

Yuchai Is Super Confident in Its Innovation

Founded in 1951, with 30 wholly-owned, holding and joint-stock subsidiaries, Guangxi Yuchai Machinery Group Co., Ltd. (hereinafter referred to as the Yuchai Group) is an internal combustion engine manufacturing base with the most complete spectrum of products in the country. In recent years, machinery manufacturing industry has been dropped off influenced by domestic and foreign economic situations, especially domestic overcapacity and unreasonable product structure. Reversely, Yuchai has sold over 3 million engines with the annualized revenues amount to RMB 40 billion. Over the years, as China ’ s largest engine R&D manufacturing base, Yuchai adjusts and optimizes its industrial structure and constantly strengthens its capacity for independent innovation. Therefore, the key technology continues to be the top in the sector for further keeping its own top leader in the industry. Innovation-Driven In 2013, seven world-class diesel-engine products for high-s...

How to Read Alarm Codes From SmartGen Genset Controller

Auto Module Control Panel is the configuration for nobody on duty controlling generators. This kind of panel adopts auto module control system, with large LCD display to show the menu, such as SmartGen controller. Features:   1. SmartGen 6110 can receive remote output signal from ATS and realize auto start and stop of generators. 2. SmartGen 6310 can realize all functions of 6110, add RS232 interface which can communicate with PC to realize remote operation.  3. SmartGen 6410 Auto Mains Failure controller, can realize all functions of 6310, furthermore can detect  ATS and control directly. The alarm of diesel generator controller is not the amount of stop alarm, which does not affect the normal operation of diesel generator. When the alarm occurs, the unit will not stop, and when the alarm conditions do not exist, the amount of warning will automatically disappear.  Today Starlight manufacturer mainly shares alarm codes for diesel generato...

How to know and solve faults of genset voltage transformer

 Today Starlight Power shares the common faults for voltage transformer of diesel generator set. Hope it is helpful to you. 1) The insulation between iron chips is damaged. Fault phenomenon: temperature rises during operation. The possible causes of the failure are: poor insulation between iron chips, bad use of environmental conditions or long-term operation under high temperature, which promote the insulation aging between iron chips. (2) Poor contact between grounding plate and iron core. Fault phenomenon: there is discharge sound between iron core and oil tank during operation. Cause of failure: the grounding plate is not inserted tightly, and the mounting screw is not tightened. (3) The iron core is loose. Fault phenomenon: abnormal vibration or noise during operation. The cause of failure: the iron core clamp is not clamped, and the iron chip is loose. (4) Turn to turn short circuit of winding. Fault phenomenon: during operation, the temperature rises, there is ...