Diesel Engine Cylinder Head Installation and Removal



The object of the measurement is to determine selection of the cylinder head gasket. Clean the mating surface, the cylinder block sealing surfaces and the cylinder head. Use cleaning spirits and 885516 Gasket scraper. Install spacers (3) and 9998678 Gauge rod (1) on the engine block sealing surface. Set the dial indicator (2) to ”0”.

15 NOTICE! All pistons must be measured at TDC. Piston height above the Volvo engine block must be measured at measuring points (1) and (2) on all pistons. Pay attention to the measuring points, since the piston crown is domed.

16 Check that the piston is in its uppermost position, TDC. Place the dial indicator on the piston at measuring points (1) and (2). Read off and note the value on the dial indicator.

17 Compare the highest noted value with the table below. Determine the appropriate cylinder head gasket.
18 NOTICE! Check the contact surface before installation. Pay attention to the guide sleeves (1).
19 Position the cylinder head gasket with the marking toward the flywheel.
Cylinder Head, Installation

20 Lift the cylinder head into place. Pay attention to the guide sleeves.
21 NOTICE! Use new cylinder head bolts.
Lubricate the cylinder head bolts. Install the cylinder head bolts.
NOTICE! Tighten the bolts in in sequence, as
illustrated.
Tighten in three steps:
Step 1: 50 Nm (36.9 lbf. ft.)
Step 2: 130 Nm (95.9 lbf. ft.)
Step 3: 90°
22 Install the pushrods.
Rocker arm bridges and rocker arms,
installation
23 NOTICE! The push rods must not be under compression due to valve overlap during installation.
Install the rocker bridge with rocker arms. Align it with the pushrods and valves.
Tightening torque: 30 Nm (22.1 lbf. ft.)
24 Connect the fuel return line (1). Hold the adapter secure (2) and fit the hollow screw (3).
Tightening torque: 29 Nm (21.4 lbf. ft.)
25 Set the valve clearance according to Valves, Adjustment page 49.
26 Install the injectors according to Injector, Change page 123.

27 Install the common rail unit according to 23-7, Common Rail, Change.
28 Install the inlet manifold according to Intake Manifold, Change page 143.
29 Install the exhaust manifold according to Exhaust Manifold, Change page 152.
30 Install the turbocharger according to Turbo, Change page 174.
31 Install the thermostat housing according to 26-2, Thermostat Housing, Change.
32 Install the air filter housing.
33 Install new oil filters and fill with engine oil according to Oil filter, Change page 94.
34 Fill with coolant according to Coolant, Change page 187.
35 Turn the main switch on.
36 Start the engine and perform a function check.

Cylinder Head, Removal
TAD752GE, TAD753GE, TAD754GE
Tools:
885516 Gasket scraper
9998678 Gauge rod
NOTICE! The main switch must be in the off position before work is begun.
1 Cooling system drained; refer to Coolant, Change page 187.
2 Oil drained.

Removal

3 Remove the air filter housing.
4 Remove the turbocharger according to Turbo, Change page 174.
5 Remove the exhaust manifold; refer to Exhaust
Manifold, Change page 152.
6 Remove the inlet manifold; refer to Intake Manifold, Change page 143.
7 Remove the thermostat housing; refer to 26-2, Thermostat Housing, Change.

IMPORTANT!

Work on the fuel system demands exceptional cleanliness. Install protective plugs in open connections.
8 Remove the common rail unit according to 23-7, Common Rail, Change.
9 Remove the injectors; refer to Injector, Change page 123.
Rocker arm bridge, removal
10 Remove the cable holders (2 pcs.) and move them aside.
11 Undo the rocker arm bridge bolts alternately.
12 Remove the rocker arm bridge with rocker arms.

13 Mark up the valve yokes.
14 Remove the push rods (1).
15 Remove the valve yokes (2).
16 Remove the wiring connectors (1) and the cable holder nuts (2).
17 Lift away the wiring.

18 Remove the injector sleeve.

19 Remove the cylinder head bolts.
20 Attach a lifting eye to the front of the cylinder head.
21 Connect straps to the lifting eyes and lift the cylinder head to remove it.

Cylinder head, installation

Cylinder head gasket
22 The object of the measurement is to determine the selection of cylinder head gasket.
23 Clean the mating surface, the cylinder block sealing surfaces and the cylinder head. Use cleaning spirits and 885516 Gasket scraper.
24 Place spacing washers (3), 9998678 Gauge rod
(1) on the engine block sealing surface and set the dial indicator (2) to ”0”.

NOTICE! All pistons must be measured at TDC. 25 Piston height above the engine block must be
measured at two points (1) and (2) on all pistons. Pay attention to the measuring points, since the
piston crown is domed.

26 Check that the piston is in its uppermost position, TDC.
Place the dial indicator on the piston at measuring points (1) and (2).
Read off and note the value on the dial indicator.

NOTICE! Make sure the surface is clean before application. 28 Position the cylinder head gasket with the marking toward the flywheel.
Pay attention to the guide sleeves (1).

Cylinder Head

29 Lift the cylinder head into place. Pay attention to the guide sleeves.


NOTICE! Use new cylinder head bolts.
30 Lubricate the cylinder head bolts.
31 Install the cylinder head bolts.
NOTICE! Tighten the bolts in numerical order, as illustrated.
32 Tighten in three steps:
Step 1: 40 Nm (29.5 lbf.ft.)
Step 2: 95 Nm (70.1 lbf.ft.)
Step 3: 180°

33 Install the injector sleeve.
34 Check the harness seal.
35 Fit the wiring connectors (1) with lock washers, and tighten the plastic nuts (2).
36 Connect the harness terminal to the wiring connector
(1).
37 Allow the cable holder to hang free from the engine.
38 Fit the push rods (1).
39 Lubricate the valve stems.
40 Replace the valve yoke (2) in accordance with the earlier marking.



Comments

Popular posts from this blog

New Yuchai engine YC6K600-D30 power for diesel generator 50Hz

Technical Parameters of Boduan 500KW Weichai Generator Set 6M33D572E200

  The 6M33D633E200 diesel engine is a special-purpose diesel engine for land-based power generation in the M33 series. It is a new-structure power generation diesel engine with a centrally - located turbocharger developed by Weichai Power Co., Ltd. in 2016. Continuous Power (COP): The maximum power at which the diesel engine can run continuously under a constant load with no limit on the annual operating hours. It is the ISO standard power. Prime Power (PRP): The maximum power at which the diesel engine can run continuously under variable loads with no limit on the annual operating hours. It is an ISO standard power that allows a 10% overload. Standby Power (ESP): The maximum power in a certain variable - power series that the diesel engine can operate for up to 200 hours per year. It is an ISO standard power with limited fuel consumption.   Operating Conditions and Applications of Baudouin  500KW Weichai Generator Set  Diesel Engine Power Classification Operating Co...

Yuchai Is Super Confident in Its Innovation

Founded in 1951, with 30 wholly-owned, holding and joint-stock subsidiaries, Guangxi Yuchai Machinery Group Co., Ltd. (hereinafter referred to as the Yuchai Group) is an internal combustion engine manufacturing base with the most complete spectrum of products in the country. In recent years, machinery manufacturing industry has been dropped off influenced by domestic and foreign economic situations, especially domestic overcapacity and unreasonable product structure. Reversely, Yuchai has sold over 3 million engines with the annualized revenues amount to RMB 40 billion. Over the years, as China ’ s largest engine R&D manufacturing base, Yuchai adjusts and optimizes its industrial structure and constantly strengthens its capacity for independent innovation. Therefore, the key technology continues to be the top in the sector for further keeping its own top leader in the industry. Innovation-Driven In 2013, seven world-class diesel-engine products for high-s...